The Rail Capital Maintenance project includes Rail Maintenance of Way (MOW) activities and Rail Maintenance of Equipment (MOE) activities in accordance with TTF eligibility requirements.
Limits: Rail Capital Maintenance
| Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
|---|---|---|---|---|---|---|
| Capital Acquisition | STATE | $0 | $0 | $4.032 | $5.790 | $34.797 |
| Program Year Totals: | ||||||
| Total FY24-FY27 Cost: | Total FY24-FY33 Cost: | |||||
| All costs in millions. | ||||||