This new federal-aid funding category established under the IIJA/BIL provides for projects that will reduce transportation emissions, as well as the development of carbon reduction strategies. A carbon reduction strategy is required to identify projects and strategies to support the reduction of transportation emissions. NJDOT’s Statewide Carbon Reduction Strategy is due to the federal government by the middle of November 2023. DVRPC is also be pursuing the creation of a regional Carbon Reduction Strategy in the FY24 UPWP.

Limits: DVRPC metropolitan region
Air Quality Code: NRS

FY2024 TIP for NJ Program Years (in Millions)

PhaseFundFY24FY25FY26FY27LFY28-33
ConstructionCR-PHILA$2.628$2.680$2.734$2.789$17.943
ConstructionCR-TRENTON$0.677$0.691$0.705$0.719$4.625
Program Year Totals:$3.305$3.371$3.439$3.508
Total FY24-FY27 Cost:$13.623Total FY24-FY33 Cost:$36.191 
All costs in millions.

No milestones are available for this project.