D2215 | (Camden County)
Four (4) curb extensions with possible rainwater harvesting features, 3 thermoplastic crosswalks, and a Rectangular Rapid-Flashing Beacon at Collings Avenue at Atlantic, Park, and Lakeview Drive intersection will be installed. These improvements were identified in the Connect 2020 Bicycle and Pedestrian Master Plan and a DVRPC funded Pop-up Demonstration project, "All Aboard Atlantic". An educational component will also be included. The project was selected from the FY23-24 DVRPC Travel Options Program (TOP).
Limits: Gateway to Downtown Collingswood (TOP)
| Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
|---|---|---|---|---|---|---|
| Construction | STBGP-PHILA | $0.218 | $0 | $0 | $0 | $0 |
| Construction | LOCAL | $0.054 | $0 | $0 | $0 | $0 |
| Program Year Totals: | ||||||
| Total FY24-FY27 Cost: | Total FY24-FY33 Cost: | |||||
| All costs in millions. | ||||||