15385 | (Burlington County)
This project will mill/pave the shoulder area and include treatment on the existing mainline pavement within the project limits. Sidewalk improvements, ADA compliance, traffic signal upgrades and guide rail upgrades will be included as well.
Limits: Nixon Drive to Route 295
| Phase | Fund | FY24 | FY25 | FY26 | FY27 | LFY28-33 |
|---|---|---|---|---|---|---|
| Construction | BFP | $0 | $0 | $8.130 | $0 | $0 |
| Program Year Totals: | ||||||
| Total FY24-FY27 Cost: | Total FY24-FY33 Cost: | |||||
| All costs in millions. | ||||||