❮ Back

11344 |

This program was initiated from a Federal Highway Administration (FHWA) request of the NJDOT to complete an Americans with Disabilities Act (ADA) Curb Ramp Inventory, and to develop a Curb Ramp Implementation Program. A priority list of locations that are missing ADA curb ramps was developed, and funding provided by this program will be applied to projects that are missing ADA curb ramps statewide.

Limits: ADA Curb Ramp Implementation

FY2024 TIP for NJ Program Years (in Millions)

PhaseFundFY24FY25FY26FY27LFY28-33
ConstructionSTBGP-FLEX$1.000$1.000$1.000$1.000$6.000
ConstructionSTATE$0.030$0.030$0.030$0.030$0.180
Program Year Totals:
Total FY24-FY27 Cost:Total FY24-FY33 Cost: 
All costs in millions.

No milestones are available for this project.