Comment
15302 | Route 41 and Deptford Center Road (Deptford Twp, Gloucester County)
This project will provide intersection improvements that will increase capacity of left turn movements from Deptford Center Road to Rt. 41 Northbound. The current configuration for this movement is single left turn lane, which has contributed to congestion and delays for left-turn vehicles.
Limits: Deptford Center Road Intersection
Air Quality Code: R1
Phase | Fund | FY26 | FY27 | FY28 | FY29 | LFY30-35 |
---|---|---|---|---|---|---|
Right of Way | NHPP | $0 | $1.400 | $0 | $0 | $0 |
Construction | NHPP | $0 | $0 | $0 | $0 | $9.400 |
Program Year Totals: | $0 | $1.400 | $0 | $0 | ||
Total FY26-FY29 Cost: | $1.400 | Total FY26-FY35 Cost: | $10.800 | |||
All costs in millions. |
Phase | Milestone | Estimated Date |
---|---|---|
Concept Development Initiated | 2017-03-01 | 2017-03-01 |
Develop Community Profile | 2017-06-09 | 2017-07-13 |
Develop Alternatives | 2017-06-19 | 2017-10-11 |
Purpose & Need Statement Completed | 2017-12-21 | 2017-12-21 |
Conduct Proposed Traffic Analysis | 2017-12-26 | 2018-01-03 |
Hold Public Information Center | 2018-05-11 | 2018-05-23 |
Authorize PE Funding | 2019-09-26 | 2019-10-24 |
Concept Development Complete | 2022-05-16 | 2022-05-16 |
Hold Public Information Center | 2018-05-11 | 2018-05-23 |
Environmental Document Complete | 2022-09-19 | 2022-09-19 |
Authorize Final Design | 2022-11-23 | 2022-12-07 |
Authorize ROW | 2023-08-15 | 2023-09-12 |
Authorize Utility Work | 2023-11-20 | 2024-01-03 |
ROW Availability | 2024-11-25 | 2024-11-25 |
PS&E Certified | 2024-12-10 | 2024-12-10 |
Receive Authorize to Advertise | 2024-12-11 | 2024-12-17 |
Contract Awarded | 2025-02-25 | 2025-02-25 |
Substantial Completion | 2026-05-19 | 2026-05-19 |