5c Guiderail Upgrade Program (DB #X201), Statewide – Decrease ERC Phase
Background/Analysis/Issues:
NJDOT has requested that DVRPC amend the FFY2026 S/TIP for New Jersey by decreasing the FFY26 Engineering/Right-of-Way/Construction (ERC) Phase of the Guiderail Upgrade Program (DB #X201) by $35 M NHPP funding from $50 M NHPP to $15 M NHPP.
Only one project funded under this program is anticipated to authorize this FFY for $15 M (Guiderail Replacement Central Contract-5). The funding that will be shifted from this program will provide resources for the Route 23, Route 80, and Route 46 Interchange (DB #9233B6) project in Passaic County ($18 M) and provide resources for remaining FFY26 authorizations for the Statewide Pavement Preservation Program (DB #X51) ($17 M). The list of remaining authorizations can be seen in the attachment.
This program provides funding for the design and construction of guiderail replacement projects Statewide. Work is performed to systemically upgrade and replace guiderail and guiderail end treatments to meet new standards adopted by the Association of State Highway Transportation Officials (AASHTO) Manual for Assessing Safety Hardware (MASH).
Financial Constraint:
Financial constraint will be maintained by making adjustments to other existing TIP projects whose schedules or costs have changed. The attached fiscal constraint charts provided by NJDOT show all of the adjustments taking place in accordance with the TIP Memorandum of Understanding. All projects listed contribute to fiscal constraint.
Conformity Finding:
The TIP's current conformity finding will not be impacted by this amendment as this project is exempt from air quality analysis.
Cost and Source of Funds:
$35 M NHPP Removed
Recommendations:
Regional Technical Committee (RTC): Will make a recommendation at the April 7, 2026, RTC
DVRPC Staff: Recommends Approval.
Action Proposed:
The Regional Technical Committee recommends the DVRPC Board approve TIP Action NJ26-018, NJDOT’s request that DVRPC amend the FFY2026 S/TIP for New Jersey by decreasing the FFY26 ERC Phase of the Guiderail Upgrade Program (DB #X201) by $35 M NHPP funding from $50 M NHPP to $15 M NHPP.