93105 | State Rd o/Darby Creek (Bridge) (Springfield Township & Upper Darby Township, Delaware County)
Bridge rehabilitation of State Road over Darby Creek.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
This road segment is included in the Delaware County Bicycle Plan.
Limits: State Road (SR 0001) between Rolling Road and State Road(SR 2026)
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
FD | 185 | $300 | $994 | $0 | $0 | $0 |
ROW | 185 | $30 | $0 | $0 | $0 | $0 |
CON | 185 | $0 | $0 | $0 | $800 | $8222 |
Program Year Totals: | $330 | $994 | $0 | $800 | ||
Total FY23-FY26 Cost: | $2,124 | Total FY23-FY34 Cost: | $10,346 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Start of Phase | 2017-09-15 |
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
FD | PS+E to District Contract Management | 2023-09-15 |
CON | Let | 2023-12-14 |
CON | Award Contract | 2024-01-13 |
CON | Start of Phase | 2024-02-12 |
CON | Notice to Proceed | 2024-02-12 |
FD | Completion of Phase | 2024-02-19 |
CON | Completion of Phase | 2026-09-06 |
CON | Physical Work Complete | 2026-12-15 |