86301 | LancasterAve/BrandywineCk (Downingtown Borough, Chester County)
This project will include the rehabilitation of the Lancaster Avenue/322 Bridge over the East Branch of Brandywine Creek in the Borough of Downingtown, Chester County.
Limits: Lancaster Ave at Brandywine Creek
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
FD | 185 | $106 | $0 | $0 | $0 | $0 |
UTL | 185 | $0 | $45 | $11 | $0 | $0 |
CON | TOLL | $0 | $0 | $0 | $0 | $0 |
CON | BRIP | $0 | $0 | $0 | $0 | $8359 |
Program Year Totals: | $106 | $45 | $11 | $0 | ||
Total FY23-FY26 Cost: | $162 | Total FY23-FY34 Cost: | $8,521 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
FD | Start of Phase | 2019-06-14 |
UTL | Plan to Utility Unit | 2019-06-15 |
CON | Final ROW Clearance | |
UTL | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
FD | PS+E to District Contract Management | 2026-05-15 |
CON | Let | 2026-08-27 |
CON | Award Contract | 2026-09-25 |
CON | Notice to Proceed | 2026-10-25 |
FD | Completion of Phase | 2026-10-25 |
CON | Start of Phase | 2026-10-25 |
CON | Physical Work Complete | 2027-09-19 |
CON | Completion of Phase | 2028-01-03 |
CON | Project Agreement End Date | 2029-03-19 |