118390 | Newtown Business Commons Sidewalk Connections (Bucks County)
This project proposes to construct approximately one half mile of five-foot wide concrete sidewalk in various areas throughout the Township Business Commons and on nearby streets. Also included will be stormwater management improvements as well as ADA curb ramp construction, improved striping and signage, benches, and landscaping.
Limits: N. Sycamore St., Terry Dr., Friends Ln., Penns Trail and Lower Dolington Rd.
Air Quality Code: A2
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
ROW | LOC | $5 | $0 | $0 | $0 | $0 |
CON | LOC | $257 | $0 | $0 | $0 | $0 |
CON | 411 | $873 | $0 | $0 | $0 | $0 |
Program Year Totals: | $1,135 | $0 | $0 | $0 | ||
Total FY23-FY26 Cost: | $1,135 | Total FY23-FY34 Cost: | $1,135 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
ROW | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
ROW | Start of Phase | 2023-02-16 |
ROW | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Completion of Phase | 2024-02-29 |
CON | Start of Phase | 2026-04-15 |
CON | Completion of Phase | 2028-12-30 |