117796 | Systemic Improvements - Vulnerable Users (Various)
This systemic project will implement roadway context appropriate traffic calming strategies with specific focus on speed management to address non-motorized roadway user safety in urban and urban-core areas.
Air Quality Code: S6
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
PE | sHSIP | $1000 | $0 | $0 | $0 | $0 |
CON | sHVRU | $0 | $0 | $2000 | $0 | $0 |
CON | sHSIP | $0 | $3000 | $0 | $0 | $0 |
Program Year Totals: | $1,000 | $3,000 | $2,000 | $0 | ||
Total FY23-FY26 Cost: | $6,000 | Total FY23-FY34 Cost: | $6,000 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
PE | Phase Approved by PMC | |
PE | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
CON | Phase Approved by PMC | |
PE | Start of Phase | 2022-10-13 |
PE | 4232 Approved by FHWA | |
PE | Completion of Phase | 2023-08-02 |
CON | Let | 2023-08-24 |
CON | Award Contract | 2023-09-23 |
CON | Start of Phase | 2023-10-23 |
CON | Notice to Proceed | 2023-10-23 |
CON | Physical Work Complete | 2025-08-15 |
CON | Completion of Phase | 2025-10-14 |
CON | Project Agreement End Date | 2027-02-13 |