❮ Back

111507 | Cramp Elementary School Traffic Safety Improvements (Philadelphia City)

Funding will establish a school slow zone near Cramp Elementary through traffic safety improvements, bumpouts & upgraded ADA ramps, speed cushions, signage, and upgraded crosswalks.

Limits: Philadelphia's Fairhill Neighborhood
Air Quality Code: S6

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
CONTOLL$0$0$0$0$0
CONTAU$0$420$0$0$0
CONTAP$1297$0$0$0$0
Program Year Totals:$1,297$420$0$0 
Total FY23-FY26 Cost:$1,717Total FY23-FY34 Cost:$1,717 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
CONPhase on Approved STIP
CONNotice to Proceed2023-07-10
CONStart of Phase2023-10-16
CONLet2023-12-07
CONAward Contract2024-01-06
CONPhysical Work Complete2025-04-23
CONCompletion of Phase2025-06-22
CONProject Agreement End Date2026-10-22