111507 | Cramp Elementary School Traffic Safety Improvements (Philadelphia City)
Funding will establish a school slow zone near Cramp Elementary through traffic safety improvements, bumpouts & upgraded ADA ramps, speed cushions, signage, and upgraded crosswalks.
Limits: Philadelphia's Fairhill Neighborhood
Air Quality Code: S6
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | TOLL | $0 | $0 | $0 | $0 | $0 |
CON | TAU | $0 | $420 | $0 | $0 | $0 |
CON | TAP | $1297 | $0 | $0 | $0 | $0 |
Program Year Totals: | $1,297 | $420 | $0 | $0 | ||
Total FY23-FY26 Cost: | $1,717 | Total FY23-FY34 Cost: | $1,717 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Phase on Approved STIP | |
CON | Notice to Proceed | 2023-07-10 |
CON | Start of Phase | 2023-10-16 |
CON | Let | 2023-12-07 |
CON | Award Contract | 2024-01-06 |
CON | Physical Work Complete | 2025-04-23 |
CON | Completion of Phase | 2025-06-22 |
CON | Project Agreement End Date | 2026-10-22 |