Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | TAP | $0 | $0 | $1000 | $0 | $0 |
Program Year Totals: | $0 | $0 | $1,000 | $0 | ||
Total FY23-FY26 Cost: | $1,000 | Total FY23-FY34 Cost: | $1,000 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Phase on Approved STIP | |
CON | Let | 2025-04-24 |
CON | Award Contract | 2025-05-24 |
CON | Notice to Proceed | 2025-06-23 |
CON | Start of Phase | 2025-06-23 |
CON | Physical Work Complete | 2026-08-28 |
CON | Completion of Phase | 2026-10-27 |
CON | Project Agreement End Date | 2028-02-26 |