111492 | Limekiln Pike Multimodal Safety Initiatives (Upper Dublin Township, Montgomery County)
Funding for this project will be used to install new five foot sidewalk along Limekiln Pike between Dreshertown Plaza and Jarrettown Elementary. New curb and drainage will be installed as required.
This project was funded via the 2018 Transportation Alternatives Set-aside Program.
Limits: Limekiln Pike between Dreshertown Plaza and Jarrettown Elementary
Air Quality Code: A2
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | TAU | $307 | $0 | $0 | $0 | $0 |
CON | TAP | $0 | $0 | $0 | $0 | $0 |
Program Year Totals: | $307 | $0 | $0 | $0 | ||
Total FY23-FY26 Cost: | $307 | Total FY23-FY34 Cost: | $307 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Final Utility Clearance | |
CON | Final ROW Clearance | |
CON | 4232 Approved by FHWA | |
CON | Phase on Approved STIP | |
CON | Let | 2023-01-12 |
CON | Award Contract | 2023-02-11 |
CON | Start of Phase | 2023-04-10 |
CON | Notice to Proceed | 2023-04-10 |
CON | Physical Work Complete | 2024-04-11 |
CON | Completion of Phase | 2024-06-07 |
CON | Project Agreement End Date | 2025-10-07 |