92641 | (Bucks County)
This project involves rehabilitating or replacing the Bridge at Dublin Pike over Morgan Creek. The improvement is a breakout of MPMS #88706 for Bridge Rehabilitation in order to process federal authorization.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: Richland Township
| Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
|---|---|---|---|---|---|---|
| UTL | STU | $85 | $0 | $0 | $0 | $0 |
| ROW | STU | $85 | $0 | $0 | $0 | $0 |
| CON | 185 | $0 | $0 | $375 | $0 | $721 |
| FD | 185 | $106 | $0 | $0 | $0 | $0 |
| ROW | 185 | $21 | $0 | $0 | $0 | $0 |
| CON | BRIP | $0 | $0 | $1500 | $0 | $2884 |
| PE | 185 | $40 | $0 | $0 | $0 | $0 |
| FD | STU | $424 | $0 | $0 | $0 | $0 |
| UTL | 185 | $21 | $0 | $0 | $0 | $0 |
| Program Year Totals: | $ | $ | $ | $ | ||
| Total FY25-FY28 Cost: | $ | Total FY25-FY36 Cost: | $ | |||
| All costs in thousands. | ||||||