90550 | (Bucks County)
This project involves rehabilitating or replacing the Creamery Road and Tohickon Creek. The improvement is a breakout of MPMS #88706 for Bridge Rehabilitation in order to process federal authorization. Improvements also include associated roadway approach reconstruction, guiderail and drainage improvements.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state
Categorical Exclusion clearance.
Limits: North of Sweetbriar Rd over Tokickon Creek on Creamery Road.
Bedminster Township, Bucks County
| Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
|---|---|---|---|---|---|---|
| UTL | STP | $0 | $46 | $0 | $0 | $0 |
| PE | 185 | $325 | $0 | $0 | $0 | $0 |
| ROW | STP | $297 | $0 | $0 | $0 | $0 |
| ROW | 185 | $74 | $0 | $0 | $0 | $0 |
| CON | 185 | $0 | $282 | $251 | $251 | $5499 |
| UTL | 185 | $0 | $12 | $0 | $0 | $0 |
| Program Year Totals: | $ | $ | $ | $ | ||
| Total FY25-FY28 Cost: | $ | Total FY25-FY36 Cost: | $ | |||
| All costs in thousands. | ||||||