84269 | (Delaware County)
This project will replace the bridge on Victory Avenue over SEPTA's Norristown High Speed Line in Delaware County. This road segment is included in the Delaware County Bicycle Plan.
Limits: Victory Ave: West Chester Pike - Cobbs Creek
| Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
|---|---|---|---|---|---|---|
| CON | 185 | $0 | $0 | $0 | $0 | $738 |
| ROW | STU | $0 | $0 | $338 | $0 | $0 |
| UTL | 185 | $0 | $0 | $0 | $580 | $0 |
| FD | BRIP | $0 | $675 | $0 | $0 | $0 |
| CON | BRIP | $0 | $0 | $0 | $0 | $2952 |
| Program Year Totals: | $ | $ | $ | $ | ||
| Total FY25-FY28 Cost: | $ | Total FY25-FY36 Cost: | $ | |||
| All costs in thousands. | ||||||