81292 |

Bridge rehabilitation or replacement of state bridge over Frankford Creek on Frankford Avenue between Torresdale Avenue and Castor Avenue in Philadelphia. Poor condition bridge breakout project from MPMS #88706.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.

Limits: Between Torresdale Avenue and Castor Avenue

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
CONTOLL$0$0$0$0$0
CON185$60$0$0$0$0
CONBRIP$2158$2915$750$1500$750
Program Year Totals:$$$$ 
Total FY25-FY28 Cost:$Total FY25-FY36 Cost:$ 
All costs in thousands.

No milestones are available for this project.