79980 | STU Reserve Line Item (Various)
This project number serves as a placeholder for unprogrammed funds and serves as a fiscal constraint balancing mechanism for project actions that occur during TIP Modifications and Amendments after a TIP is adopted.
Limits: Region-wide
Air Quality Code: NRS
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | STU | $636 | $3298 | $625 | $0 | $8572 |
CON | 581 | $738 | $1197 | $245 | $2240 | $1151 |
Program Year Totals: | $1,374 | $4,495 | $870 | $2,240 | ||
Total FY25-FY28 Cost: | $8,979 | Total FY25-FY36 Cost: | $18,702 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Start of Phase | 2009-06-15 |
CON | Completion of Phase | 2010-06-15 |
CON | Phase on Approved STIP | |
CON | Phase Approved by PMC |