17697 | Island Avenue Signal Upgrade (Philadelphia City)

Upgrade and interconnect the signal controls at six intersections including incidental stormwater improvements, incorporating preference for SEPTA Route 36; narrow the roadway to accommodate pedestrians; and simplify three intersections. This project location is included in Philadelphia’s Bike Network and is rated BF (Bike Friendly - wide shoulders or lanes).

Limits: Woodland Avenue to Bartram Avenue
Air Quality Code: 2025M

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
CONCAQ$950$0$0$0$0
Program Year Totals:$950$0$0$0 
Total FY25-FY28 Cost:$950Total FY25-FY36 Cost:$950 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
CONFinal Utility Clearance
CONStart of Phase2022-08-08
CON4232 Approved by FHWA
CONLet2022-11-03
CONPhase on Approved STIP
CONAward Contract2022-07-11
CONNotice to Proceed2023-01-30
CONPhysical Work Complete2025-09-29
CONCompletion of Phase2026-04-30
CONProject Agreement End Date2026-05-16