❮ Back

12965 | (Bucks County)

Reconstruct roadway, curbs, sidewalks, and walls. Construct new sidewalk and curbs in areas currently without them. Perform a minor relocation of one horizontal curve. Install new drainage facilities as required. Relocate affected water and sanitary sewer lines as required. A portion of the roadway from Noble St to Maple Ave is proposed to be turned back to the borough upon completion of the project. Upon completion of the project sidewalk will be in place from Grandview Hospital to the borough center.

Limits: Maple Avenue to Farmers Lane

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
CON581$0$496$496$496$1984
CONSTU$0$1985$1985$1985$7940
Program Year Totals:$$$$ 
Total FY25-FY28 Cost:$Total FY25-FY36 Cost:$ 
All costs in thousands.

No milestones are available for this project.