110963 | Manor Road Roundabout (West Brandywine Township, Chester County)
Roundabout installation at Manor Rd (SR 0082) & Cedar Knoll/Reeceville Road (SR 4005).
Limits: Manor Rd (SR 0082) & Cedar Knoll/Reeceville Road (SR 4005)
Air Quality Code: 2025M
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | sHSIP | $228 | $0 | $0 | $0 | $0 |
Program Year Totals: | $228 | $0 | $0 | $0 | ||
Total FY25-FY28 Cost: | $228 | Total FY25-FY36 Cost: | $228 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Final ROW Clearance | |
CON | Final Utility Clearance | |
CON | 4232 Approved by FHWA | |
CON | Phase on Approved STIP | |
CON | Let | 2022-10-20 |
CON | Award Contract | 2022-11-19 |
CON | Notice to Proceed | 2022-12-05 |
CON | Start of Phase | 2022-12-19 |
CON | Completion of Phase | 2024-03-19 |
CON | Physical Work Complete | 2025-03-26 |
CON | Project Agreement End Date | 2025-07-19 |