Comment
X12 | Acquisition of Right of Way (Various)
This program funds advanced acquisition and/or demolition of; key right of way parcels, easements, transportation facilities, and access and development rights, in order to preserve transportation corridors for future transportation use.
Limits: Advance Acquisition of Right of Way
Air Quality Code: X7
Phase | Fund | FY26 | FY27 | FY28 | FY29 | LFY30-35 |
---|---|---|---|---|---|---|
Right of Way | STATE | $0.200 | $0.450 | $0.450 | $0.450 | $2.900 |
Program Year Totals: | $0.200 | $0.450 | $0.450 | $0.450 | ||
Total FY26-FY29 Cost: | $1.550 | Total FY26-FY35 Cost: | $4.450 | |||
All costs in millions. |