❮ Back
Comment

T53E | Locomotive Overhaul (Various)

Funding is provided for service reliability to the locomotive fleet based on manufacturer replacement and service standards to maintain equipment through its useful life. In-house staff ensure that each locomotive engine continues to properly function in terms of reliability and fuel consumption, without being remanufactured, specified to work output or miles; and that the locomotive complies with all applicable emission standards.

Limits: Locomotive Overhaul
Air Quality Code: M3

FFY2026 Draft TIP for NJ (FFY26-FFY29) Program Years (in Millions)

PhaseFundFY26FY27FY28FY29LFY30-35
Capital AcquisitionSECT 5337$0.251$0.234$0.586$0.307$0
Capital AcquisitionSTATE$0.147$0.147$0.147$0.147$0.879
Program Year Totals:$0.398$0.381$0.733$0.454
Total FY26-FY29 Cost:$1.966Total FY26-FY35 Cost:$2.845 
All costs in millions.

No milestones are available for this project.