❮ Back
Comment

22352 | Carbon Reduction Program (Various)

Established pursuant to Section 11403 of the Infrastructure Investment and Jobs Act (IIJA). Eligibility includes establishment or operation of traffic monitoring, management, and control facilities or programs, advanced truck stop electrification systems, advanced transportation and congestion management technologies, development of infrastructure-based intelligent transportation systems capital improvements, installation of vehicle to infrastructure communications equipment, replacement of street lighting and traffic control devices, development of a carbon reduction strategy, and retrofitting of Dedicated Short Range Communication (DSRC) technology.

Limits: (null)
Air Quality Code: NRS

FFY2026 Draft TIP for NJ (FFY26-FFY29) Program Years (in Millions)

PhaseFundFY26FY27FY28FY29LFY30-35
PlanningCR-FLEX$1.000$1.000$1.000$1.000$6.000
ConstructionCR-B5K50K$0.539$0.549$0.560$0.572$3.678
ConstructionCR-B50K200K$0.196$0.200$0.204$0.208$1.339
ConstructionCR-L5K$1.314$1.341$1.367$1.395$8.974
Program Year Totals:$3.049$3.090$3.131$3.175
Total FY26-FY29 Cost:$12.445Total FY26-FY35 Cost:$32.436 
All costs in millions.

No milestones are available for this project.