Comment
18313 | Route 42 SB, Leaf Avenue Extension to Creek Road (CR 753) (Bellmawr Boro, Camden County)
This project will relocate access to Route 42 ramps further down County Route 753, and provide sufficient lane configurations to accommodate freight movement.
Limits: Leaf Avenue Extension to Creek Road (CR 753)
Air Quality Code: R1
Phase | Fund | FY26 | FY27 | FY28 | FY29 | LFY30-35 |
---|---|---|---|---|---|---|
Preliminary Engineering | NHPP | $2.339 | $0 | $0 | $0 | $0 |
Design | NHPP | $0 | $0 | $0.700 | $0 | $0 |
Right of Way | NHPP | $0 | $0 | $0 | $3.400 | $0 |
Construction | NHPP | $0 | $0 | $0 | $0 | $8.000 |
Program Year Totals: | $2.339 | $0 | $0.700 | $3.400 | ||
Total FY26-FY29 Cost: | $6.439 | Total FY26-FY35 Cost: | $14.439 | |||
All costs in millions. |
Phase | Milestone | Estimated Date |
---|---|---|
Concept Development Initiated | 2017-08-14 | 2017-08-14 |
Purpose & Need Statement Completed | 2018-03-14 | 2018-03-14 |
Develop Alternatives | 2020-10-19 | 2021-02-05 |
Develop Community Profile | 2020-12-02 | 2021-03-05 |
Conduct Proposed Traffic Analysis | 2020-12-04 | 2021-02-05 |
Hold Public Information Center | 2022-04-18 | 2022-04-29 |
Authorize PE Funding | 2023-06-27 | 2023-07-25 |
Concept Development Completed | 2023-09-06 | 2023-09-06 |