13304 | Intelligent Transportation System Resource Center (Various)
This program includes the development of a statewide Intelligent Transportation Systems (ITS) Strategic Plan, ITS Deployment Plan, and a Work Zone Mobility Monitoring Program. The center will also conduct research, operational tests, evaluation of deployment scenarios and strategies, training and outreach to develop best practices for implementation of ITS.
Air Quality Code: S7
Phase | Fund | FY26 | FY27 | FY28 | FY29 | LFY30-35 |
---|---|---|---|---|---|---|
Construction | STBGP-FLEX | $3.500 | $3.500 | $3.500 | $3.500 | $21.000 |
Program Year Totals: | $3.500 | $3.500 | $3.500 | $3.500 | ||
Total FY26-FY29 Cost: | $14.000 | Total FY26-FY35 Cost: | $35.000 | |||
All costs in millions. |