❮ Back
Comment

04324 | Electrical Load Center Replacement, Statewide (Various)

This program provide provides funding for the betterment of existing highway lighting facilities when those facilities do not comply with current electrical codes and/or replacement equipment is not available. Due to high traffic volumes, maintenance of these existing facilities is hazardous to NJDOT personnel. The use of high-mast lighting will be investigated. ROW acquisition may be required.

Limits: Electrical Load Center Replacement, Statewide
Air Quality Code: NRS

FY2026 Draft TIP for NJ Program Years (in Millions)

PhaseFundFY26FY27FY28FY29LFY30-35
ConstructionSTATE$6.000$6.000$6.000$6.000$36.000
Program Year Totals:$6.000$6.000$6.000$6.000
Total FY26-FY29 Cost:$24.000Total FY26-FY35 Cost:$60.000 
All costs in millions.

No milestones are available for this project.