❮ Back
Comment

18313 | Route 42 SB, Leaf Avenue Extension to Creek Road (CR 753) (Bellmawr Boro, Camden County)

This project will relocate access to Route 42 ramps further down County Route 753, and provide sufficient lane configurations to accommodate freight movement.

Limits: Leaf Avenue Extension to Creek Road (CR 753)
Air Quality Code: R1

FFY2026 Draft TIP for NJ (FFY26-FFY29) Program Years (in Millions)

PhaseFundFY26FY27FY28FY29LFY30-35
DesignNHPP$0$0$0$0$3.000
Right of WayNHPP$0$0$0$0$3.400
ConstructionNHPP$0$0$0$0$10.500
Program Year Totals:$0$0$0$0
Total FY26-FY29 Cost:$0Total FY26-FY35 Cost:$16.900 
All costs in millions.

Milestones

PhaseMilestoneEstimated Date
Concept Development Initiated2017-08-142017-08-14
Purpose & Need Statement Completed2018-03-142018-03-14
Develop Alternatives2020-10-192021-02-05
Develop Community Profile2020-12-022021-03-05
Conduct Proposed Traffic Analysis2020-12-042021-02-05
Hold Public Information Center2022-04-182022-04-29
Authorize PE Funding2023-06-272023-07-25
Concept Development Completed2023-09-062023-09-06