13014 | Clay Ridge Road Bridge Over Beaver Creek (CB #30) (Tinicum Township, Bucks County)
Reconstruction of a 1909 reinforced concrete arch bridge located in Tinicum Township. The bridge is 25 feet long and is identified as County Bridge #30. A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: Over Beaver Creek
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
ROW | 183 | $11 | $0 | $0 | $0 | $0 |
ROW | LOC | $3 | $0 | $0 | $0 | $0 |
ROW | BOF | $57 | $0 | $0 | $0 | $0 |
UTL | LOC | $4 | $0 | $0 | $0 | $0 |
UTL | 183 | $13 | $0 | $0 | $0 | $0 |
UTL | BOF | $67 | $0 | $0 | $0 | $0 |
CON | BOF | $0 | $2690 | $0 | $0 | $0 |
CON | 183 | $0 | $504 | $0 | $0 | $0 |
CON | LOC | $0 | $168 | $0 | $0 | $0 |
Program Year Totals: | $155 | $3,362 | $0 | $0 | ||
Total FY23-FY26 Cost: | $3,517 | Total FY23-FY34 Cost: | $3,517 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Start of Phase | 2021-06-01 |
FD | Completion of Phase | 2016-10-14 |
PE | Start of Phase | 2011-09-01 |
PE | Completion of Phase | 2016-04-14 |
PE | N. E. P. A. Approval | 2021-05-03 |
ROW | Plan to ROW Unit | 2021-08-02 |
UTL | Plan to Utility Unit | 2021-08-02 |
FD | PS+E to District Contract Management | 2022-06-15 |
CON | Let | 2023-06-08 |
CON | Award Contract | 2023-07-08 |
CON | Start of Phase | 2023-08-07 |
CON | Notice to Proceed | 2023-08-07 |
CON | Physical Work Complete | 2023-09-27 |
CON | Completion of Phase | 2023-11-26 |
CON | Project Agreement End Date | 2025-03-27 |